Proposed Construction and Completion of Paradom 33Kv substation, Sibu


Project Description

This project is to build new 33kV substation to cater for electricity needs at Paradom, Sibu area. The items consist of building of one Substation building, 2 transformer, Oil Interceptor and external associate civil work. The construction is expected to complete in 2014.

Client
SARAWAK ENERGY BERHAD (SEB)

Location of Project
SIBU, SARAWAK

Year of Design/Study
2012

Year of Project Implementation
2013

Project Cost
RM1,000,000.00